Newly built facilities will be tested at TPP Sofia East

02 December 2021

Starting today, tests of a new turbine will be carried out at the Sofia East TPP.

The technological tests will last 2 hours within 7 days. The tests are part of the mandatory requirements for the implementation of the project and Siemens, as a manufacturer of new equipment. The testing process may create increased noise levels outside the plant.

Notification letters have been sent to the Sofia Municipality and all interested institutions for the planned activities.

The successful completion of the modernization of the plant will increase the quality of service and the continuity of heat supply in the surrounding areas.

The tests will be performed on the days from 02.12.2021 to 10.12.2021, except on weekends.